The module computes the primary consolidation settlement of clay layers under a foundation, following the stress history of every slice: initial state, excavation unloading and swelling, reloading up to the preconsolidation pressure, virgin compression beyond it, and — with Cv — the development with time. It is a one-dimensional analytical calculation: hydrostatic pore pressure, Boussinesq stress increase, Terzaghi consolidation.
1Scope
Every layer of the profile is clay: no other kind of soil can be entered. The immediate (elastic) settlement belongs to the Elastic Settlement modules — one for cohesive soils, one for granular soils — and the Settlement 2D module combines them over a profile of both kinds of layer: consolidation plus immediate settlement in the clay layers, immediate settlement in the granular ones.
2Stress path
The calculation is never a single step from the initial to the final stress. The excavation reduces the effective stress and the clay swells along its unloading line (Cs). When the structure reloads it, the clay first retraces that line back to σ′v0 — the heave is recovered — then recompresses with Cr up to σ′p and, when the final stress exceeds σ′p, compresses along the virgin line (Cc). σ′p is the historical maximum and is not reduced by the excavation.
The unloading–reloading loop therefore closes at the initial stress: a load that only restores the removed overburden brings every slice back to where it started, and without a net increase of the effective stress there is no settlement relative to the original ground, whatever Cs and Cr are.
3Slices and initial stresses
Every layer between the foundation level and the calculation depth zlim is divided into slices of thickness Δz (cut at the water table); every stress is evaluated at the slice midpoint.
γ above the water table, γsat below it. The stresses of the original ground are the reference for every later phase.
4Preconsolidation pressure
One definition per model. OCR = 1 is a normally consolidated clay: σ′p = σ′v0 and any loading beyond the initial stress is virgin compression. A laboratory σ′p below σ′v0 is raised to σ′v0 with a warning — under-consolidated clay is outside the scope.
5Excavation — unloading and swelling
The removed load is the initial effective overburden at the excavation base (the water table is unchanged, so below it the buoyant weight is removed). Iexc is the Boussinesq influence of the excavation plan, or 1 for a wide excavation. Heave is negative: settlement positive, heave negative throughout. When Cs is not given, Cs = Cr is used and reported.
6Stress increase — Boussinesq
Rectangle B × L under its centre: Iz = 4·Icorner(m = B/2z′, n = L/2z′) with the Newmark corner factor
(the arctangent term is increased by π when V < m²n²). Strip of width B under its centre line: Iz = (α + sin α)/π with α = 2·atan(B/2z′). At z′ = 0, Iz = 1. Off the centre line — for the colour-band fields — the rectangle is split into corner rectangles at the point and the strip uses the general solution with the two edge angles.
7Depth of the settlement calculation
The stress increase under a foundation falls with depth but never becomes zero, so the sum of the slice compressions needs a lower end — the calculation depth zlim.
With the influence depth rule the layers are compressed down to the depth where the Boussinesq stress increase under the centre of the foundation has fallen to p of the applied pressure; 10 % is the common choice. The same influence factor governs the unloading of an excavation of the same plan, so the depth is the same whether it is read on qgross or qnet. The depth grows with the size of the foundation: with p = 10 %, z′ ≈ 2.09 B for a square, 2.55 B for L = 1.5 B, 2.92 B for L = 2 B, 4.33 B for L = 5 B and 6.34 B for a strip (1.40 B, 1.71 B, 1.94 B, 2.68 B and 3.13 B with p = 20 %). A 20 × 30 m raft reaches about 51 m below its base.
When the soil profile ends above zlim, its last layer is taken to continue down to zlim with the same properties (and, for the time analysis, to end there). When it reaches below zlim, the soil below that depth is not compressed; a layer cut by zlim keeps its whole thickness for the drainage path. With the Bottom of the profile rule the calculation stops at the last layer, as over rock or dense gravel; the report gives the stress increase that is still acting there.
Another criterion used in practice compares the stress increase with the effective overburden (Δσ = 0.2 · σ′v0); it reaches deeper under a heavily loaded small footing and stops much higher under a lightly loaded wide raft. The influence-depth rule of the module depends on the geometry only, which keeps the whole compressible zone of a wide raft in the sum.
8Compression regimes
With f = ΔH/(1+e0) for the slice, and σ′exc ≤ σ′v0 ≤ σ′p:
| Condition | Slice compression on reloading |
|---|---|
| σ′exc ≤ σ′final ≤ σ′v0 | Sb = Cs·f·log10(σ′final/σ′exc) — part of the heave recovered, no compression beyond the initial state |
| σ′v0 < σ′final ≤ σ′p | Sb = Cs·f·log10(σ′v0/σ′exc) + Sr = Cr·f·log10(σ′final/σ′v0) |
| σ′v0 < σ′p < σ′final | Sb + Sr = Cr·f·log10(σ′p/σ′v0) + Sv = Cc·f·log10(σ′final/σ′p) |
| σ′p = σ′v0 < σ′final (normally consolidated) | Sb + Sv = Cc·f·log10(σ′final/σ′v0) |
| σ′final < σ′exc | further swelling with Cs (negative) |
Without an excavation σ′exc = σ′v0 and Sb = 0: the classical recompression and virgin compression from the initial stress.
9Where the settlement is measured from
An excavation followed by a foundation is a sequence of phases, and the settlement of the foundation depends on the reference its displacements are measured from — the choice Displacements after the excavation of the Excavation stage:
- Kept — from the original ground (default). The heave of the excavation phase is shown on its own; the settlement of the foundation is the net deformation at the end of the loading, S = Sc + Sheave = Σ compression beyond σ′v0. A load no larger than the removed overburden gives S = 0, and when it is smaller the ground ends above its original level (reported, the settlement 0).
- Reset to zero before loading. The displacements of the excavation phase are set to zero and the settlement is measured from the heaved excavation base: S = Sc = Sb + Sr + Sv. The recompression of the heave counts as settlement — a fully compensated foundation settles by as much as the base had heaved. This is the answer when the excavation stays open long enough for the heave to develop before the structure is built.
Both measures are always printed; the choice decides which one is reported as the settlement of the foundation, drawn on the time curve and written in the conclusion.
10mv method
A separate, linear calculation path: the same mv serves the unloading (heave = −mv·(σ′v0 − σ′exc)·ΔH) and the reloading (Sc = mv·(σ′final − σ′exc)·ΔH, of which the part up to σ′v0 is the heave recovered, Sb). Being linear, its loop closes by itself. Cc, Cr, Cs and e0 are not mixed into it.
11Time-dependent consolidation
Hdr = H for single drainage and H/2 for double drainage, with H the thickness of the layer below the foundation level (down to zlim for a last layer that continues beyond the profile). Layers with different Cv and Hdr consolidate at different rates, so the curve of the whole profile is the sum of the layer curves; its own t50 and t90 are read from that sum. Below Tv = 0.05 the early-time solution U = 2√(Tv/π) is used. The curve is that of the loading settlement Sc; the swelling is taken as complete before the loading. With the displacements kept from the original ground the curve is drawn from the heave, S(t) = Sheave + Σ Ui(t)·Sc,i, and ends at the net deformation; with the displacements reset it starts at zero.
12Colour-band fields
The Contours and Settlement views paint a quantity over the whole cross section in colour bands between its minimum and maximum, the legend giving the value at every third boundary. The stresses of the original ground depend on depth only; the stress changes follow Boussinesq at every point below the foundation level (zero above it); strain, settlement, heave and net deformation are computed with the same stress path as the slices between the foundation level and zlim, and S(z) at a point is the compression of the soil between it and zlim — so the value at the foundation level on the centre line is the settlement of the foundation, and S(zlim) = 0. The drawings reach zlim when it lies below the profile.
Classes for the deformation fields. Settlement, heave and strain are largest under the load and small at depth. With equal bands the whole lower part of the section would fall into the first band and the picture would read as if the movement stopped just under the foundation. These fields are therefore painted in classes with the limits 1 · 1.5 · 2 · 3 · 5 · 7 × 10n, from 1/300 of the maximum up, with the colours spread over the classes, and every limit is written in the legend. The stresses, the modulus and a net deformation that changes sign keep the thirty-six equal bands.
13Sign convention and assumptions
- Settlement positive, heave negative: Snet = Sc + Sheave; the settlement of the foundation is Snet (from the original ground) or Sc (displacements reset after the excavation). The selector next to the units in the header switches the display to the convention in which the vertical displacement is positive upward (settlement negative, heave positive) — in the results, the tables, the drawings and the report; the engine, the derivation in the Calculations tab and the strains and stresses (compression positive) stay classical.
- Foundation level = excavation base (ground surface without an excavation).
- Water table unchanged by the excavation; hydrostatic pore pressure.
- Stresses on the vertical through the centre of the foundation for the slices; the fields extend them over the section.
- e0 is the initial void ratio in every phase.
- Secondary compression (Cα) is not included in this version.
Every assumption that applies to a model is listed with its results (Warnings and assumptions).
14Outside the scope
- Granular layers and the immediate (elastic) settlement of any soil — the Elastic Settlement modules and Settlement 2D.
- SPT- or CPT-based sand settlement, rock settlement.
- 2D/3D or finite-element consolidation.
- Bearing capacity, liquefaction.
15References
- Terzaghi, K. (1943). Theoretical Soil Mechanics. Wiley.
- Newmark, N.M. (1935). Simplified computation of vertical pressures in elastic foundations. Univ. of Illinois Bulletin 429.
- Das, B.M. (2016). Principles of Geotechnical Engineering, 9th ed. Cengage.
- Holtz, R.D., Kovacs, W.D., Sheahan, T.C. (2011). An Introduction to Geotechnical Engineering, 2nd ed. Pearson.
- Craig, R.F., Knappett, J.A. (2012). Craig’s Soil Mechanics, 8th ed. Spon.
From theory to your own design
Find the consolidation settlement of your own foundation in minutes
- The settlement of every layer and the stress path of each
- The settlement–time curve
- Colour bands of stress and settlement over the section
- A clean calculation report, saved as a PDF. Online: nothing to install, no dongle, on a phone, a tablet or a PC